Electrical Construction Revenue
The Company accepts contracts on a fixed price, unit price and service agreement basis. Revenue from fixed price construction contracts are recognized on the percentage-of-completion method, measured by the ratio of costs incurred to date, to the estimated total costs to be incurred for each contract. Revenue from unit price contracts and service agreements are recognized as services are performed. Unit price contracts are billed at an agreed upon price per unit of work performed. Revenue from service agreements are billed on either a man-hour or man-hour plus equipment basis. Terms of the Company’s service agreements may extend for periods beyond one year.
The Company’s contracts allow it to bill additional amounts for change orders and claims. Additionally, the Company considers a claim to be for additional work performed outside the scope of the contract, contested by the customer. Historically, claims relating to electrical construction work have not been significant. It is the Company’s policy to include revenue from change orders and claims in contract value only when they can be reliably estimated and realization is considered probable, in accordance with ASC Topic 605-35-25-30 and ASC Topic 605-35-25-31, Revenue Recognition for Construction Type Contracts.
The asset, “costs and estimated earnings in excess of billings on uncompleted contracts” represents revenue recognized in excess of amounts billed. The liability, “billings in excess of costs and estimated earnings on uncompleted contracts” represents billings in excess of revenue recognized.
Contract costs include all direct material, direct labor, subcontractor costs and indirect costs related to contract performance, such as supplies, tools and equipment maintenance. General and administrative costs are charged to expense as incurred. Provisions for estimated losses on uncompleted contracts are made in the period in which such losses are determined. Changes in job performance, job conditions, estimated profitability and final contract settlements may result in revisions to costs and income and are recognized in the period in which the revisions are determined.