2.    COSTS AND ESTIMATED EARNINGS IN EXCESS OF BILLINGS ON UNCOMPLETED CONTRACTS
 
At December 31, 2013, costs and estimated earnings in excess of billings on uncompleted contracts (unbilled) consist of:
 
 
U.S. Government
Commercial
Total
Costs incurred on uncompleted contracts
$259,050,407
$62,502,116
$321,552,523
Estimated earnings
95,590,879
30,694,605
126,285,484
 
354,641,286
93,196,721
447,838,007
Less billings to date
272,783,120
62,733,921
335,517,041
Costs and estimated earnings in excess of billings on uncompleted contracts
$81,858,166
$30,462,800
$112,320,966
       
At December 31, 2012, costs and estimated earnings in excess of billings on uncompleted contracts (unbilled) consist of:
 
U.S. Government
Commercial
Total
 
Costs incurred on uncompleted
     
Contracts
$214,888,101
$42,636,753
$257,524,854
Estimated earnings
85,320,636
23,782,285
109,102,921
 
300,208,737
66,419,038
366,627,775
Less billings to date
215,743,090
42,631,694
258,374,784
Costs and estimated earnings in excess of billings on uncompleted contracts
$84,465,647
$23,787,344
$108,252,991
 
 
 
The above amounts are included in the accompanying balance sheets under the following captions at December 31, 2013 and December 31, 2012:
 

 
 
2013
2012
Costs and estimated earnings in excess of billings on
   
uncompleted contracts
$ 112,597,136
$ 108,909,844
Billings in excess of costs and estimated earnings on
   
uncompleted contracts
 (276,170)
 (656,853)
     
Totals
$ 112,320,966
$ 108,252,991
 
Unbilled costs and estimated earnings are billed in accordance with applicable contract terms.  As of December 31, 2013, approximately $30 million of the balances above are not expected to be collected within one year.  There are no amounts billed under retainage provisions.

 
Revisions in the estimated gross profits on contracts and contract amounts are made in the period in which the circumstances requiring the revisions occur. During the years ended December 31, 2013, 2012 and 2011, the effect of such revisions in total estimated contract profits resulted in a decrease to the total gross profit to be earned on the contracts of approximately $3,700,000, $1,300,000 and $3,000,000, respectively, from that which would have been reported had the revised estimate been used as the basis of recognition of contract profits in prior years.
 

Although management believes it has established adequate procedures for estimating costs to complete on uncompleted open contracts, it is at least reasonably possible that additional significant costs could occur on contracts prior to completion.



us-gaap:LongTermContractsOrProgramsDisclosureTextBlock